Andrew (Boy) Charlton Pool is currently closed to carry out critical, extensive maintenance work and transition the pool heating system to electric heat pumps.

Male sitting and looking over at Andrew (Boy) Charlton Pool

Published Wed, 31 Jan 2024

We’re carrying out critical and extensive maintenance work to Andrew (Boy) Charlton Pool.

The pool operates seasonally and closes from 1 May to 31 August every year.

Works will begin in May after the pool closes. We expect to reopen the pool on 1 September 2025, in time for the start of the summer season.

What works and improvements will take place?

The tiles and waterproof membranes will be replaced on the 50m outdoor pool and the smaller 20m pool.

Essential maintenance will be carried out on the pool’s concrete and steel structure. A new lift will be installed and the timber replaced in the grandstand and concourse decking.

Maintaining outdoor pools, particularly in difficult to access marine environments like this one, can be challenging and often take longer than other outdoor pools that don't extend over the harbour.

On top of this important maintenance work, we’ll also futureproof this vital piece of community infrastructure by replacing the gas heating system with electric heat pumps.

We’re committed to tackling climate change and we aim to reach our net zero goal by 2035. All our operations are powered by 100% renewable electricity and transitioning away from polluting fossil fuels will be crucial to reducing emissions in our operations.